You can tell an awful lot from a quick glance at a delivery board. As for all tools and metrics, a delivery board may not give answers, but will offer very good questions.
.jpg)
The value stream has three teams and each team has a board (more detail about their boards later).
The value stream has adopted a 6-week iteration, with iteration 14 one week longer to include the holidays. The Sync Event is in the first week of the iteration, probably the beginning of the week judging by its position.
The value stream has decided to show the next 2 iterations at a lower level of detail. They are currently at the end of week 3.
There is a cross-team dependency shown as a less visible arrow between teams Octopus and Gorillas.
The teams seem to have an agreed and shared definition of done reported on the board. Also, there is a link to the strategic roadmap for the value stream and/or company.

Showing the start of iteration 12, between planning and the Sync Event.
Some board features:
Some questions arising from the board: